Etihad Rail, the developer and operator of the UAE National Rail Network, has announced that it has completed the tracklaying works of the main line in the northern emirates of Sharjah and Ras Al Khaimah, as part of the last package of Stage Two of the project.
The network's main line extends from Ghuweifat on the border of the Kingdom of Saudi Arabia, and passes through the emirates of Abu Dhabi, Dubai, Sharjah and Ras Al Khaimah.
Moving full steam ahead, Etihad Rail will start laying tracks in Fujairah in the coming weeks, thus bringing it closer towards the completion of the UAE National Rail Network as per schedule.
The line in Sharjah extends over 45 km and is part of the last package of the project, which is 145 km in length. The work related to connecting the emirate to the main line saw more than 11.7 million work hours within 25 months.
Around 2,900 workers and engineers were part of the project, which involved the track laying works and running quality checks for the new line.
The line in Ras Al Khaimah, which extends over 5.7 km and connects the emirate to the main line, recorded more than 1.3 million work hours in 25 months involving 350 workers and engineers.
Deputy Project Manager Khuloud Al Mazrouei said: "Etihad Rail has made remarkable strides by completing the main works for the UAE National Rail Network and connecting it to the main lines in Sharjah and Ras Al Khaimah, thus bringing us closer than ever to completing the network on schedule and achieving our objective of providing an efficient and sustainable transport network that links the country’s emirates, and connects the UAE with the region."
"This plays a key role in opening up new prospects in the logistics and transport industry, driving social development, and providing promising economic opportunities in the UAE and the region across a range of sectors," she stated.
Al Mazrouei said: "We are moving on track towards perpetuating our success story, with the support of our exceptional national and global talents who are contributing to enhancing the UAE’s infrastructure sector."
The last package of Stage Two, which runs for 145 km from Sharjah to Fujairah port, passing through Ras Al Khaimah, saw important developments. In May, Etihad Rail began track laying operations of the package.
The line in the last package of Stage Two has 54 bridges and 20 animal crossings. It also has 9 tunnels which extend over 6.9 km along Al Hajar Mountains, and include the longest tunnel in the GCC for heavy cargo, which extends over 1.8 km,. she added.-TradeArabia News Service